PRECAUTIONS

  1. Flushing valve is installed and preset at factory. DO NOT ADJUST OR REMOVE. Installation shall have an approved backflow preventer installed in the supply line to the fixture, if required by local plumbing codes.
  2. Take extra caution to locate wires, gas lines and pipes that are hidden in the wall.
  3. These instructions were drawn up using 1/2" dry wall.
  4. Manufacturer is not responsible for injury or mishap that may occur during installation.
new_install1 (9K)STEP 1. On a studded wall,before drywall, determine height of Mister Miser Urinal using the following chart. Install 2" x 2"s to hold urinal on the inside of both studs, and set them back 1 5/16" from front of studs. This is based on using 1/2" drywall.
new_install3 (10K)STEP 3. Attach water inlet with a 1/8" NPT x 1/4" straight brass compression fitting into Top of urinal, at pre-threaded location according to local and state plumbing codes.
heightchart (22K)


*Heights are determined by measurements from the floor to the top of the urinal door in open position. You may also install at height which is most comfortable with you. The water supply connection is approximately 4" above the top of the door and centered. The center of the trap is approximately 14 inches below the top of the door and empties to the right side. Before proceeding, pull nylon hinge pin out with needle nose pliers, raise door and twist out to remove.
STEP 4. Use this template to cut hole in drywall. Place the drywall over the face of the face of the urinal and screw into the studs. Run a bead of caulking around the face of the urinal.



new_install4 (8K) STEP 5. Connect to drain in accordance with local and state plumbing codes. Trap opening is 1 1/2" ABS plastic.

new_install6 (9K)STEP 6. Attach door to hinges and insert nylon hinge pin.

new_install2 (10K)STEP 2. Screw all four ears of the urinal into 2" x 2"s. Make sure urinal is level. Install drain, according to state and local codes.
new_install7 (7K)STEP 7. This is what the Mister Miser Urinal should look like upon completion. To use, open door and aim on lower trough. To flush, simply close door and release. The door will pop back open approximately 1/4" after closing.
bottom_logo (4K)
newlogo (41K)

Retrofit Installation Instructions

PRECAUTIONS

  1. Flushing valve is installed and preset at factory. DO NOT ADJUST OR REMOVE. Installation shall have an approved backflow preventer installed in the supply line to the fixture, if required by local plumbing codes.
  2. Take extra caution to locate wires, gas lines and pipes that are hidden in the wall.
  3. These instructions were drawn up using 1/2" dry wall.
  4. Manufacturer is not responsible for injury or mishap that may occur during installation.
STEP 1. Locate the general area that you wish to put your urinal and then locate the studs. Cut a hold 14 1/2"x16 1/2" between studs. Make sure you have a 2 3/4" clearance between top of unit and top of square hole.
retrofit_install4 (10K)STEP 4. Attach water inlet with a 1/8" NPT x 1/4" straight brass compression fitting into top of urinal according to local and state plumbing codes. Screw ears into 1 1/2" x 1 1/2" nailer boards after carefully leveling the urinal.
heightchart (22K)


*Heights are determined by measurements from the floor to the top of the urinal door in open position. You may also install at height which is most comfortable with you. The water supply connection is approximately 4" above the top of the door and centered. The center of the trap is approximately 14 inches below the top of the door and empties to the right side. Before proceeding, pull nylon hinge pin out with needle nose pliers, raise door and twist out to remove.
retrofit_install5 (10K)STEP 5. Install 1 1/2" drain and insert vent stack into "T" running along side the urinal, according to local and state plumbing codes.

retrofit_install6 (10K)STEP 6. This is an example of what your hook-up should look like before finishing.

STEP 2. Screw a 1 1/2" x 1 1/2" nailer board, 14" long, on both studs, set back 1 3 /8" from the face of drywall. (Based on using 1/2" drywall.)
retrofit_install7 (9K)STEP 7. Attach door to hinges and insert nylon hinge pin.
retrofit_install3 (10K)STEP 3. If vent stack is required by code, you may cut off ears on right side and use second set of ears for installation, leaving vent stack space. Also, cut 1/4" from left side ears to position urinal to left side of opening.
retrofit_install8 (7K)STEP 8. This is what the Mister Miser Urinal should look like upon completion. To use, open door and aim on lower trough. To flush, simply close door and release. The door will pop back open approximately 1/4" after closing.